Hackberry Sherry Ln & Billy Dale Ct Improvements, Frisco, TX

Denton County

Owner Reference: HACK23018

Bid Date: 12/03/2024 at 10:00am
12 Days until bid date

Estimate: $200,000

Trades: Concrete Contractor: Sidewalks, Curbs, Gutters, Driveways, Handicap ADA Ramps. Pedestrian Improvements, CIP Concrete NIGP 913-47, Earthwork & Paving Contractor, Asphalt, Land Clearing, Path & Trail Construction: General Engineering Contractor, Pipeline Contractor: Water Mains, Water Lines, Sewer Lines + Related Structures; Includes Pipe Inspection Camera, Sewer Pump System, Sewer Connection, Septic Tanks & Systems Contractor: OnSite Sewage Facility (OSSF); CIPP liners, Roadway Drainage, Stormwater, Manhole Covers & Valve Boxes, Ditches, Culverts, Shoulder Work, Underderdrains, Dewatering, Road S, Excavation & Grading Contractor: Blasting, Boring, Trenching, Backfill, Digging - General Engineering Contractor

Sherry Ln - Remove existing and construct app. 1,215 LF of reinforced concrete pavement. Billy Dale Ct - Remove existing and construct app. 350 LF of asphalt pavement, with cul-de-sac. Waterline extension, sanitary sewer line extension, drainage, grading. Bonds required. Prevailing wages.

Mark Hill ext. 115
 Login or create an account
 Login or create an account

Owner: City of Hackberry TX

Published 11/20/2024 on Construction Bid Source

DISCLAIMER: The bid notifications listed on Construction Bid Source are compiled from various sources and updated daily. It is the responsibility of each user, whether browsing publicly or logged in, to contact the project owner directly for the purpose of bidding and obtaining additional project details. Construction Bid Source does not assume any responsibility for omissions or errors in the information provided.